172 Copyright © Acronis, Inc., 2000-2010
Working with backup plans and tasks
Actions on backup plans and tasks
The following is a guideline for you to perform operations with backup plans and tasks.
To Do
Create a new backup plan,
or a task
Click
New, then s elect one of th e fol lowi ng:
Backup plan (p. 181)
Recovery tas k (p. 199)
Vali dation task (p. 217)
View details of a plan/task
Click
Backup plan
View details.
In the Plan Details (p. 178) window, review the plan details.
Click
Task
View details.
In the Task Details (p. 176) wi ndow, revi ew th e tas k detail s.
View plan's/task's log
Click
Backup plan
View log.
You will be taken to the Log (p. 179) view containing the list of the plan-r el a ted
l og entri es.
Click
Task
View log.
You will be taken to the Log (p. 179) vi ew contai ning the l ist of the tas k-rel ated
l og entri es.
Run a plan/task
Click
Backup plan
Run.
In the Run Backup Plan (p. 176) window, select the task you need to be run.
Running the backup plan starts the selected task of that plan immediately in
spite of its schedule and conditions.
Why can't I run the backup plan?
Do not have the appropriate privilege
Without the Administrator privileges on the machine, a user cannot run
plans owned by other users.
Click
Task
Run.
The tas k will be executed i mmediately in spite of its schedule and conditions.